Selection KeySelection KeyFree Mock Test
View this question in:

A project takes 36 days to complete with a certain number of workers and machines. The time required is directly proportional to the amount of work, inversely proportional to the number of workers, and inversely proportional to the square of the number of machines. If the number of workers is doubled and the number of machines is tripled, while the amount of work remains the same, how many days will the project take to complete?

(RRB Section Controller CBT-1 2026 (12 Oct 2026, Shift 1))
  1. 4
  2. 2
  3. 8
  4. 6
Answer (Detailed Solution Below)
Option 2 : 2

Detailed Solution

Concept approach

Time ∝ 1/(workers × machines²)

⇒ factor = 1/(2 × 3²) = 1/18

36/18 = 2 days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →