If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?

(SSC CHSL 2020 (14 Oct 2020, Shift 2))
  1. 15 days
  2. 16 days
  3. 18 days
  4. 20 days
Answer (Detailed Solution Below)
Option 2 : 16 days

Detailed Solution

Concept approach

Men × hours × days = constant

27 × 8 × 12 = 2592 = 18 × 9 × d

d = 2592/162 = 16 days