(A + B) can do a piece of work in 14 days. A works 3.5 days and B works for 11.5 days, then half of the work has been completed. In how many days will B do this work alone?

  1. 28 days
  2. 35 days
  3. 32 days
  4. 40 days
Answer (Detailed Solution Below)
Option 3 : 32 days

Detailed Solution

Concept approach

3.5(A + B) = 3.5/14 = 1/4; B worked 8 more days = 1/2 − 1/4 = 1/4

⇒ B = 1/32

⇒ 32 days