Three men or five women can do a piece of work in 57 days. In how many days can nine men and four women finish the same work?

(SSC CHSL Tier-1 2023)
  1. 16 days
  2. 14 days
  3. 18 days
  4. 15 days
Answer (Detailed Solution Below)
Option 4 : 15 days

Detailed Solution

Concept approach

3m = 5w = 15

⇒ m = 5, w = 3

⇒ t.w = 15 × 57; 9m + 4w

⇒ 15 × 57/(45 + 12) = 15 days

Ultra Calci trickmultiple-of-5 (cancel 19)

9 men + 4 women = 9/3 + 4/5 = 19/5 units (1 unit = 57 days)

Days = 57 ÷ (19/5) = 57 × 5/19 = 3 × 5 → multiple of 5

16 ✗ 14 ✗ 18 ✗ 15 ✓

⇒ 15 days