A and B working separately can complete a piece of work in 10 and 16 days, respectively. If they work for a day alternately, with A beginning the work, in how many day(s) will the work be completed?

(SSC CGL Tier-1 2022 (3 Dec · Shift 4 · 5:15 PM))
  1. 10¼
  2. 12¼
  3. 1¼
  4. 1/4
Answer (Detailed Solution Below)
Option 2 : 12¼

Detailed Solution

Concept approach

LCM 80: A = 8, B = 5 per day

⇒ 2 days = 13

⇒ 12 days = 78, left 2

⇒ A does 2/8 = ¼ day

⇒ 12¼ days