P can do a piece of work in 30 days and Q in 40 days. They work together for 4 days and then Q leaves. The number of days taken by P to finish the remaining work is:

(SSC CPO Paper-1 2024 (28 Jun 2024, Shift 3))
  1. 28 days
  2. 23 days
  3. 30 days
  4. 7 days
Answer (Detailed Solution Below)
Option 2 : 23 days

Detailed Solution

Concept approach

LCM(30, 40) = 120

⇒ P = 4, Q = 3

4 days × 7 = 28

⇒ left 92

P alone = 92/4 = 23 days