In a company, a piece of work can be completed in 4, 6 and 18 days alone by R, S and T, respectively. In how many days will the work be completed if they work together? (Rounded off to 2 decimal places)

(SSC CGL Tier-1 2023 (18 Jul · Shift 4 · 5:15 PM))
  1. 3.32
  2. 2.12
  3. 2.42
  4. 3.21
Answer (Detailed Solution Below)
Option 2 : 2.12

Detailed Solution

Concept approach

Total work = 36

⇒ efficiency 9 + 6 + 2 = 17

⇒ 36/17 = 2.1176 ≈ 2.12 days

⇒ B