A job is completed by 3 workers in 12 days. How many days will it take for 9 workers to complete the same job?

(SSC CGL 2026 (16 Oct, Shift 3))
  1. 6 days
  2. 3 days
  3. 4 days
  4. 5 days
Answer (Detailed Solution Below)
Option 3 : 4 days

Detailed Solution

Concept approach

Man-days = 3×12 = 36

⇒ 36/9 = 4 days