A and B can do a work in 16 days. A alone works for 8 days and B completes the remaining work in 20 days by working alone. In how much time can B do this work alone?

  1. 24 days
  2. 32 days
  3. 36 days
  4. 48 days
Answer (Detailed Solution Below)
Option 1 : 24 days

Detailed Solution

Concept approach

A+B 8 days = 1/2 work (8 days of both). B's 20 days = 8 days (with A) + 12 days alone

⇒ B alone 12 days = remaining 1/2

⇒ B full work = 24 days