Rohit started a certain piece of work and continued for 6 days. After that, he had to leave, so Suresh was called in and he completed the remaining work in 24 days. If instead Rohit had worked for 9 days before leaving, then Suresh would have completed the remaining work in just 12 days. In how many days can Rohit alone finish the entire work?

(SSC Selection Post 2026 (Higher Secondary, 23 Sep, Shift 2))
  1. 48 days
  2. 12 days
  3. 36 days
  4. 24 days
Answer (Detailed Solution Below)
Option 2 : 12 days

Detailed Solution

Concept approach

6r + 24s = 1 and 9r + 12s = 1

⇒ 12r = 1

⇒ Rohit alone = 12 days