A and B can complete a piece of work in 12 days and 6 days, respectively. Both work together for 2 days and then A leaves. B completes the remaining work alone. In how many days is the whole work completed?

(RRB NTPC Undergraduate CBT-1 2026 (19 Jun 2026, Shift 1))
  1. 6
  2. 4
  3. 5
  4. 3
Answer (Detailed Solution Below)
Option 3 : 5

Detailed Solution

Concept approach

LCM = 12

⇒ A = 1, B = 2

2 days = 6

⇒ left = 6

B alone = 6/2 = 3 days

⇒ total = 5 days