Selection KeySelection KeyFree Mock Test
View this question in:

25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?

(SSC CHSL 2020 (18 Mar 2020, Shift 1))
  1. 15 days
  2. 18 days
  3. 12 days
  4. 10 days
Answer (Detailed Solution Below)
Option 4 : 10 days

Detailed Solution

Concept approach

Total work = 25 × 16 = 400 units

In 4 days = 25 × 4 = 100

⇒ remaining 300

Now 30 men

⇒ 300/30 = 10 days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →