A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together, but C left after 4 days of starting, and A left 6 days before completion of the work. In how many days will the work be completed?

(SSC MTS 2021 (18 Oct 2021, Shift 1))
  1. 9 days
  2. 15 days
  3. 12 days
  4. 14 days
Answer (Detailed Solution Below)
Option 3 : 12 days

Detailed Solution

Concept approach

Efficiency (LCM 96): A = 6, B = 4, C = 3. Let work last T days: A works T − 6, B works T, C works 4

6(T − 6) + 4T + 3 × 4 = 96

⇒ 10T − 24 = 96

⇒ T = 12 days

⇒ option C

Ultra Calci trickLCM work

LCM 96 → A 6, B 4, C 3 per day; total T days

6(T − 6) + 4T + 3 × 4 = 96 → 10T = 120 → T = 12

⇒ 12 days