A man starts a task on the first day, another man joins him on the second day, another man joins him on the third day and this process continues until the task is completed. The task is completed in 50 days. Instead, if a group of 25 people work together on this task, then in how many days will this task be completed?

  1. 50
  2. 51
  3. 52
  4. 48
Answer (Detailed Solution Below)
Option 2 : 51

Detailed Solution

Concept approach

Man-days = 1 + 2 + … + 50 = 1275 = 25 × T

⇒ T = 51 days