A man takes 16 days to complete a project. A woman does the same work in 12 days.
They started the work together on alternate days and the man worked on the first day.
How much time will they take to complete the work?
They started the work together on alternate days and the man worked on the first day.
How much time will they take to complete the work?
(SSC CHSL 2022 (26 May 2022, Shift 2))
- 58/4 days
- 55/4 days
- 33/4 days
- 61/4 days
Answer (Detailed Solution Below)
Option 2 : 55/4 days
Detailed Solution
Concept approach
Man 1/16, woman 1/12: LCM 48
⇒ 3 and 4 per day (total work 48)
2 days = 7; 12 days = 42
Day 13 man: 45; woman needs 3 at 4/day = 3/4 day
Total = 13 3/4 = 55/4 days
एक पुरुष किसी परियोजना को पूरा करने में 16 दिन लेता है। एक महिला वही कार्य 12 दिनों में करती है।
उन्होंने एकांतर दिनों में साथ मिलकर कार्य शुरू किया और पुरुष ने पहले दिन कार्य किया।
उन्हें कार्य पूरा करने में कितना समय लगेगा?
(SSC CHSL 2022 (26 May 2022, Shift 2))
- 58/4 days
- 55/4 days
- 33/4 days
- 61/4 days
उत्तर (विस्तृत हल नीचे)
विकल्प 2 : 55/4 days
विस्तृत हल
कॉन्सेप्ट से हल
पुरुष 1/16, महिला 1/12: LCM 48
⇒ 3 और 4 प्रति दिन (कुल 48)
2 दिन = 7; 12 दिन = 42
13वाँ दिन पुरुष: 45; महिला को 3 चाहिए, 4/दिन
⇒ 3/4 दिन
कुल = 13 3/4 = 55/4 दिन