A and B can complete the work in 9 days and 36 days, respectively. A starts the work and they work alternately, one person working each day. In how many days will the entire work be completed?

(SSC CGL 2026 (24 Oct, Shift 2))
  1. 12 1/2 days
  2. 9 1/4 days
  3. 14 1/4 days
  4. 18 1/2 days
Answer (Detailed Solution Below)
Option 3 : 14 1/4 days

Detailed Solution

Concept approach

LCM 36: A = 4/day, B = 1/day. 2 days = 5 units

⇒ 7 cycles (14 days) = 35. Left 1

⇒ A does it in 1/4 day. Total = 14¼ days.