A can complete a work in 10 days and B in 15 days. How long will it take them to finish the work if they work together?

(SSC CGL 2026 (5 Oct, Shift 3))
  1. 6 days
  2. 7 days
  3. 8 days
  4. 9 days
Answer (Detailed Solution Below)
Option 1 : 6 days

Detailed Solution

Concept approach

LCM 30: A = 3, B = 2

⇒ 5 per day

Time = 30/5 = 6 days