A, B and C can do a piece of work in 30, 20 and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish?

  1. 8 4/13 days
  2. 4 8/9 days
  3. 9 3/8 days
  4. 3 9/13 days
Answer (Detailed Solution Below)
Option 3 : 9 3/8 days

Detailed Solution

Concept approach

Total = 60; A 2, B 3, C 6. Day 1 (A+B) = 5, day 2 (A+C) = 8

⇒ 13 per 2 days. 8 days = 52; day 9: 5

⇒ 3 left; day 10: 3/8

⇒ 9 3/8 days