A and B complete a work in 24 and 30 days, respectively, working 10 hours per day.
The work is to be done in two shifts. The morning shift is for 6 hours and the evening shift is for 4 hours. On the first day, A works in the morning and B works in the evening, and they interchange their shifts every day. On which day did the work get completed?
The work is to be done in two shifts. The morning shift is for 6 hours and the evening shift is for 4 hours. On the first day, A works in the morning and B works in the evening, and they interchange their shifts every day. On which day did the work get completed?
(SSC CPO Paper-1 2023 (05 Oct 2023, Shift 1))
- 21st day
- 24th day
- 30th day
- 27th day
Answer (Detailed Solution Below)
Option 4 : 27th day
Detailed Solution
Concept approach
Work in hours: A = 240 h, B = 300 h
⇒ LCM 1200
⇒ A = 5/h, B = 4/h
odd day: A 6h + B 4h = 30 + 16 = 46; even day: B 6h + A 4h = 24 + 20 = 44
2 days = 90
⇒ 13 pairs = 26 days = 1170
left 30
⇒ done on 27th day
A और B प्रतिदिन 10 घंटे कार्य करते हुए एक कार्य को क्रमशः 24 और 30 दिनों में पूरा करते हैं।
कार्य दो पालियों में किया जाना है। सुबह की पाली 6 घंटे की और शाम की पाली 4 घंटे की है। पहले दिन A सुबह और B शाम को कार्य करता है, और वे प्रतिदिन अपनी पालियाँ आपस में बदल लेते हैं। कार्य किस दिन पूरा हुआ?
(SSC CPO Paper-1 2023 (05 Oct 2023, Shift 1))
- 21वें दिन
- 24वें दिन
- 30वें दिन
- 27वें दिन
उत्तर (विस्तृत हल नीचे)
विकल्प 4 : 27वें दिन
विस्तृत हल
कॉन्सेप्ट से हल
घंटों में काम: A = 240 h, B = 300 h
⇒ LCM 1200
⇒ A = 5/h, B = 4/h
विषम दिन: A 6h + B 4h = 30 + 16 = 46; सम दिन: B 6h + A 4h = 24 + 20 = 44
2 दिन = 90
⇒ 13 जोड़े = 26 दिन = 1170
शेष 30
⇒ 27वें दिन पूरा