A can complete a work in 8 days and B can complete the same work in 11 days. How long will they take, if both work together?

(SSC CPO Paper-1 2022 (10 Nov 2022, Shift 3))
  1. 4¹²⁄₁₇ days
  2. 5¹²⁄₁₉ days
  3. 4¹¹⁄₁₉ days
  4. 4¹²⁄₁₉ days
Answer (Detailed Solution Below)
Option 4 : 4¹²⁄₁₉ days

Detailed Solution

Concept approach

Total work = 88 (LCM): A = 11, B = 8 per day

⇒ 19/day

88/19 = 4 12/19 days