Three men and 4 women can do a piece of work in 7 days, whereas 2 men and 1 woman can do it in 14 days. Seven women will complete the same work in:

(SSC CGL Mains 2019 (15 Nov 2020))
  1. 8 days
  2. 9 days
  3. 10 days
  4. 12 days
Answer (Detailed Solution Below)
Option 3 : 10 days

Detailed Solution

Concept approach

7(3M + 4W) = 14(2M + W)

⇒ 14W = 7M

⇒ M = 2W

Total = 7 × (6W + 4W) = 70W

⇒ 7 women: 70/7 = 10 days