A, B and C working together completed a job in 18 days. However, C worked only for the first five days, when 35% of the job was done. How many days will C take to complete the job alone?

  1. 30 days
  2. 25 days
  3. 36 days
  4. 50 days
Answer (Detailed Solution Below)
Option 4 : 50 days

Detailed Solution

Concept approach

Last 13 days A + B did 65%

⇒ A + B = 5% per day

⇒ first 5 days A + B did 25%, so C did 10% in 5 days

⇒ C alone 50 days