Numan does half of Gagan's work in 4/5 of the time. If together they take 16 days to complete a work, how long will Gagan take to complete that work alone?

(SSC CGL Tier-1 2022 (5 Dec · Shift 1 · 9:00 AM))
  1. 23 days
  2. 24 days
  3. 25 days
  4. 26 days
Answer (Detailed Solution Below)
Option 4 : 26 days

Detailed Solution

Concept approach

Numan takes 4/5 of Gagan's time for half of Gagan's work

⇒ Numan's full job = 2 × 4/5 = 8/5 of Gagan's time

Time ratio Gagan : Numan = 5 : 8

⇒ together = 40/13 units = 16 days

⇒ 5 units = 26 days

Ultra Calci trickunits + T126 ratio

Reading: Numan does half of Gagan's work in 4/5 of the time

⇒ efficiency N : G = (1/2) ÷ (4/5) = 5 : 8

Together 13 units = 1 work in 16 days

⇒ work = 208; Gagan 8 per day

208 ÷ 8 = 26 ✓

⇒ 26 days