A team of 15 volunteers can plant a plot of saplings in 8 hours. On the day of the project, 5 volunteers do not show up. Assuming all volunteers work at the same pace, how long will it take the remaining team to complete the planting?

(SSC CGL 2026 (16 Oct, Shift 1))
  1. 12 hrs
  2. 11.5 hrs
  3. 10 hrs
  4. 9.6 hrs
Answer (Detailed Solution Below)
Option 1 : 12 hrs

Detailed Solution

Concept approach

Work = 15×8 = 120 man-hours; 10 volunteers

Time = 120/10 = 12 hrs