A, B and C alone can do a piece of work in 5, 55 and 66 days, respectively. They all started the work together, but A left after 4 days. In how many days was the whole work completed?

(RRB NTPC Graduate CBT-1 2025 (17 Jun 2025, Shift 2))
  1. 2
  2. 6
  3. 7
  4. 3
Answer (Detailed Solution Below)
Option 2 : 6

Detailed Solution

Concept approach

LCM = 330: A = 66, B = 6, C = 5

4 days together = 4 × 77 = 308

⇒ remaining 22

(B + C) = 11

⇒ 2 days

⇒ total = 6 days

Ultra Calci trickLCM work units

LCM 330: A 66, B 6, C 5 units/day

⇒ together 77/day; 4 days = 308 units

left 330 − 308 = 22 units by B + C = 11/day

⇒ 2 days

⇒ 4 + 2 = 6 days (2 ✗ 3 ✗ 7 ✗)

⇒ 6