Selection KeySelection KeyFree Mock Test
View this question in:

A team of linguists is translating the text on an ancient monolith. Linguist A and linguist B working together can translate it in 12 days, linguist B and linguist C working together can do it in 15 days, while A and C working together can do it in 20 days. All three of them work together on the monolith for 6 days. Then, A and B are relocated to another site. How many more days will be required by C to finish the remaining task alone?

(SSC CGL 2026 (6 Oct, Shift 1))
  1. 20 days
  2. 22 days
  3. 24 days
  4. 25 days
Answer (Detailed Solution Below)
Option 3 : 24 days

Detailed Solution

Concept approach

2(A+B+C) = 1/12 + 1/15 + 1/20 = 12/60

⇒ A+B+C = 1/10

6 days = 6/10

⇒ left 4/10

C = 1/10 − 1/12 = 1/60

⇒ days = (4/10) × 60 = 24

Ultra Calci trickLCM work / efficiency

LCM(12, 15, 20) = 60 units

⇒ A+B = 5, B+C = 4, A+C = 3

⇒ A+B+C = 12 ÷ 2 = 6

⇒ C = 6 − 5 = 1

6 days × 6 = 36

⇒ left 24

⇒ 24 ÷ 1 = 24 days ✓

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →