A team of linguists is translating the text on an ancient monolith. Linguist A and linguist B working together can translate it in 12 days, linguist B and linguist C working together can do it in 15 days, while A and C working together can do it in 20 days. All three of them work together on the monolith for 6 days. Then, A and B are relocated to another site. How many more days will be required by C to finish the remaining task alone?
(SSC CGL 2026 (6 Oct, Shift 1))
- 20 days
- 22 days
- 24 days
- 25 days
Answer (Detailed Solution Below)
Option 3 : 24 days
Detailed Solution
Concept approach
2(A+B+C) = 1/12 + 1/15 + 1/20 = 12/60
⇒ A+B+C = 1/10
6 days = 6/10
⇒ left 4/10
C = 1/10 − 1/12 = 1/60
⇒ days = (4/10) × 60 = 24
Ultra Calci trickLCM work / efficiency
LCM(12, 15, 20) = 60 units
⇒ A+B = 5, B+C = 4, A+C = 3
⇒ A+B+C = 12 ÷ 2 = 6
⇒ C = 6 − 5 = 1
6 days × 6 = 36
⇒ left 24
⇒ 24 ÷ 1 = 24 days ✓
भाषाविदों की एक टीम एक प्राचीन शिलालेख का अनुवाद कर रही है। भाषाविद A और B मिलकर इसे 12 दिनों में, B और C मिलकर 15 दिनों में, और A और C मिलकर 20 दिनों में अनुवाद कर सकते हैं। तीनों 6 दिनों तक साथ काम करते हैं। फिर A और B को दूसरी जगह भेज दिया जाता है। शेष काम अकेले पूरा करने में C को कितने और दिन लगेंगे?
(SSC CGL 2026 (6 Oct, Shift 1))
- 20 दिन
- 22 दिन
- 24 दिन
- 25 दिन
उत्तर (विस्तृत हल नीचे)
विकल्प 3 : 24 दिन
विस्तृत हल
कॉन्सेप्ट से हल
2(A+B+C) = 1/12 + 1/15 + 1/20 = 12/60
⇒ A+B+C = 1/10
6 दिन = 6/10
⇒ बचा 4/10
C = 1/10 − 1/12 = 1/60
⇒ दिन = (4/10) × 60 = 24
अल्ट्रा कैलसी ट्रिकLCM work / efficiency
LCM(12, 15, 20) = 60 इकाई
⇒ A+B = 5, B+C = 4, A+C = 3
⇒ A+B+C = 12 ÷ 2 = 6
⇒ C = 6 − 5 = 1
6 दिन × 6 = 36
⇒ शेष 24
⇒ 24 ÷ 1 = 24 दिन ✓