Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

(SSC CGL Mains 2019 (16 Nov 2020))
  1. 22
  2. 18
  3. 14
  4. 20
Answer (Detailed Solution Below)
Option 1 : 22

Detailed Solution

Concept approach

28(2M + 7W) = 11(6M + 16W)

⇒ 56M + 196W = 66M + 176W

⇒ M = 2W

Total = 28 × 11W = 308W; 5M + 4W = 14W

⇒ 308/14 = 22 days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →