A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, in how many days would half of the work be completed?

  1. 5 days
  2. 5 2/3 days
  3. 10 1/4 days
  4. 10 days
Answer (Detailed Solution Below)
Option 1 : 5 days

Detailed Solution

Concept approach

Total = 36, half = 18; A 4, B 3

⇒ 7 per 2 days. 4 days = 14; day 5 A does 4

⇒ 18

⇒ 5 days