Selection KeySelection KeyFree Mock Test
View this question in:

A can complete a work in 18 days, while B can complete it in 12 days. B worked on it for 4 days. How long will A take to finish the remaining work?

(SSC CGL Tier-1 2023 (17 Jul · Shift 4 · 5:15 PM))
(SSC CGL 17.07.2023)
  1. 16 days
  2. 12 days
  3. 14 days
  4. 10 days
Answer (Detailed Solution Below)
Option 2 : 12 days

Detailed Solution

Concept approach

B in 4 days = 4/12 = 1/3

⇒ left 2/3

⇒ A = 18 × 2/3 = 12 days

⇒ B

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →