Maya does 60% of a work in 18 days. She then calls Puja and both together finish the rest of the work in 6 days. How many days would Puja alone take to complete the work?

(SSC CGL 2026 (27 Oct, Shift 2))
  1. 20 days
  2. 24 days
  3. 25 days
  4. 30 days
Answer (Detailed Solution Below)
Option 4 : 30 days

Detailed Solution

Concept approach

Maya: 60% in 18 days

⇒ 100% in 30 days. Together: rest 40% in 6 days

⇒ total 15 days. 1/15 − 1/30 = 1/30

⇒ Puja = 30 days.