6 men and 10 boys, as well as 2 men and 20 boys can finish the same work in 12 days. In how many days will 10 boys finish the same work?

(SSC MTS 2021 (02 Nov 2021, Shift 1))
  1. 24
  2. 26
  3. 16
  4. 30
Answer (Detailed Solution Below)
Option 4 : 30

Detailed Solution

Concept approach

6m + 10b = 2m + 20b

⇒ 4m = 10b

⇒ m = 2.5b

Work = (15b + 10b) × 12 = 300 boy-days

⇒ 10 boys = 30 days

⇒ option D

Ultra Calci trickefficiency units

6m + 10b = 2m + 20b → 4m = 10b → m = 5, b = 2 units

work = (30 + 20) × 12 = 600; 10 boys = 20 per day → 30 days

⇒ 30