Avi and Bindu can complete a project in four and twelve hours, respectively. Avi begins project at 5 a.m., and they work alternately for one hour each. When will the project be completed?

(SSC CHSL 2022 (24 May 2022, Shift 3))
  1. 9 a.m.
  2. 11 a.m.
  3. 1 p.m.
  4. 10 a.m.
Answer (Detailed Solution Below)
Option 2 : 11 a.m.

Detailed Solution

Concept approach

Per 2 hours: 1/4 + 1/12 = 1/3

⇒ 4 h = 2/3

5th hour Avi: 2/3 + 1/4 = 11/12; 6th hour Bindu: +1/12 = 1

6 hours from 5 a.m.

⇒ 11 a.m.