If A and B can do a piece of work in 20 days, and A alone can do the same work in 30 days, then in how many days can B alone complete the same work?

(SSC MTS 2021 (12 Oct 2021, Shift 1))
  1. 60
  2. 40
  3. 75
  4. 50
Answer (Detailed Solution Below)
Option 1 : 60

Detailed Solution

Concept approach

A + B = 1/20, A = 1/30

⇒ B = 1/20 − 1/30 = 1/60

⇒ 60 days. (LCM 60: 3 − 2 = 1 unit/day

⇒ 60 days)

⇒ A.