Selection KeySelection KeyFree Mock Test
View this question in:

A project can be completed by 2 men and 5 women in 8 days while 4 men and 6 women can complete the same project in 5 days. How many men will be required to complete this project in 4 days?

(SSC MTS 2022 (07 Jul 2022, Shift 1))
  1. 8
  2. 10
  3. 9
  4. 12
Answer (Detailed Solution Below)
Option 1 : 8

Detailed Solution

Concept approach

8(2m + 5w) = 5(4m + 6w)

⇒ 16m + 40w = 20m + 30w

⇒ m = 2.5w. Work = 8 × (5w + 5w) = 80w

⇒ in 4 days 20w per day

⇒ 20w/2.5w = 8 men.

Ultra Calci trickefficiency units

2m + 5w = 8 days, 4m + 6w = 5 days → 16m + 40w = 20m + 30w → m = 5, w = 2 units

work = (10 + 10) × 8 = 160 → in 4 days 40 per day → 40/5 = 8 men

⇒ 8