(A + B) together can complete a job in 8 days. B alone and C alone can each finish the same job in 12 days. A and B commence the work and work for 4 days, whereupon A leaves; B continues for 2 more days and then he leaves too. C now starts working and finishes the job. How many days will C require?

  1. 3 days
  2. 4 days
  3. 5 days
  4. 6 days
Answer (Detailed Solution Below)
Option 2 : 4 days

Detailed Solution

Concept approach

Total = 24; A+B = 3, B = 2, C = 2. 4 days = 12; B 2 days = 4

⇒ left 8

⇒ C needs 4 days