A group of 150 men can do a work in a certain number of days. On the 1st day all men work, on the 2nd day 4 men leave, on the 3rd day another 4 leave, and so on. In this process the group takes 8 days more. Find the number of days taken by the group.

(SSC CPO 2019)
  1. 25
  2. 23
  3. 17
  4. 8
Answer (Detailed Solution Below)
Option 1 : 25

Detailed Solution

Concept approach

(0 + 4 + 8 + … n terms) = 150 × 8

⇒ n/2 × 4(n − 1) = 150 × 8

⇒ n(n − 1) = 600

⇒ n = 25

Ultra Calci tricksum = n × middle + T23 test options

Total days N, men 150, 146, … (AP): man-days = N × middle term = N × (150 − 2(N − 1)); original days = N − 8, man-days = 150(N − 8)

N = 25: 25 × 102 = 2550 = 150 × 17 ✓

N = 23: 2438 ≠ 2250 ✗ N = 17: 2006 ≠ 1350 ✗ N = 8 ✗

⇒ 25