View this question in:

350 workers can do work in 60 days. It is decided to add some workers just to end the work 4 days before of scheduled time. How many should more workers be added?

(SSC MTS 2023 (16 May 2023, Shift 1) memory-based)
  1. 60
  2. 25
  3. 55
  4. 75
Answer (Detailed Solution Below)
Option 2 : 25

Detailed Solution

Concept approach

Work = 350 × 60 = 21000

56 days

⇒ workers = 21000/56 = 375

more = 375 − 350 = 25