Selection KeySelection KeyFree Mock Test
View this question in:

Kapil, Mohan, and Raju can do a piece of work separately in 18, 36, and 54 days. They started the work together but Mohan left the work 8 days before the completion of work and Raju left the work 6 days before the completion of the work. Find the (approximate) time in which the work is completed.

(SSC GD Constable 2023 (01 Feb 2023, Shift 2))
  1. 19 days
  2. 13 days
  3. 15 days
  4. 12 days
Answer (Detailed Solution Below)
Option 2 : 13 days

Detailed Solution

Concept approach

Total work = LCM(18, 36, 54) = 108; rates 6, 3, 2

Total time T: 6T + 3(T − 8) + 2(T − 6) = 108

11T = 144

⇒ T ≈ 13 days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →