A and B can do a piece of work in 12 days and 28 days, respectively. Both work for 3 days and then A leaves. How long (in days) will B take to complete the remaining work?

(RRB NTPC Undergraduate CBT-1 2026 (17 Jun 2026, Shift 1))
  1. 20
  2. 19
  3. 18
  4. 17
Answer (Detailed Solution Below)
Option 3 : 18

Detailed Solution

Concept approach

LCM(12, 28) = 84

⇒ A = 7, B = 3

3 days = 30

⇒ left = 54

B alone = 54/3 = 18 days