When A alone does a piece of work, he takes 25 days more than the time taken by A and B to do the work together. On the other hand, B alone takes 16 days more than the time taken by A and B to do the work together. How many days will A and B, working together, take to do the work?

(SSC CPO Paper-1 2023 (04 Oct 2023, Shift 1))
  1. 24
  2. 20
  3. 23
  4. 22
Answer (Detailed Solution Below)
Option 2 : 20

Detailed Solution

Concept approach

If A+B take t days: A = t + 25, B = t + 16

t² = 25 × 16 = 400

⇒ t = 20 days