A can do a piece of work in 40 days and B in 60 days. Both of them start working together and 4 days before the scheduled completion, A drops out. By how many days is the work extended beyond the normal schedule?

  1. 10 days
  2. 8 days
  3. 8.33 days
  4. 6 days
Answer (Detailed Solution Below)
Option 4 : 6 days

Detailed Solution

Concept approach

Total = 120; A 3, B 2

⇒ schedule 24 days. In 20 days = 100

⇒ left 20 ÷ B (2) = 10 days

⇒ total 30

⇒ extended by 6 days