A and B undertake a project worth ₹36,000. A alone can do the work in 25 days. They worked together for 5 days. For the next five days, B worked alone. After that, A substituted B and completed the remaining work in 5 days. The share of A in the earnings is:

(SSC CPO Paper-1 2023 (04 Oct 2023, Shift 1))
  1. ₹14,400
  2. ₹21,400
  3. ₹14,600
  4. ₹21,600
Answer (Detailed Solution Below)
Option 1 : ₹14,400

Detailed Solution

Concept approach

Total work done by A: 5 days (together) + 5 days (last) = 10 days

⇒ 10/25 = 2/5 of the work. A's share = 2/5 × 36000 = ₹14,400

⇒ option A.