P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in 13/5 days, then in how many days can Q alone finish 66 2/3% of the same work?

(SSC CGL Mains 03.02.2022)
  1. 5
  2. 4
  3. 2
  4. 3
Answer (Detailed Solution Below)
Option 4 : 3

Detailed Solution

Concept approach

P in 5 days = 5/18

⇒ left 13/18 in 13/5 days

⇒ P + Q = 5/18

⇒ Q = 4/18 = 2/9

⇒ whole work 4.5 days

⇒ 2/3 of work = 3 days

Ultra Calci trickLCM work

LCM 90 units: P = 5/day; P alone 5 days = 25; remaining 65 in 13/5 days

⇒ together 65 ÷ 2.6 = 25/day

Q = 25 − 5 = 20/day; 66⅔% = 2/3 of 90 = 60 units

⇒ 60 ÷ 20 = 3

5 ✗ 4 ✗ 2 ✗

⇒ 3 days