If 450 men can finish construction of an apartment in 20 days, then how many men are needed to complete the same work in 30 days?

(SSC CGL Tier-1 2022 (1 Dec · Shift 3 · 2:30 PM))
  1. 150
  2. 300
  3. 400
  4. 250
Answer (Detailed Solution Below)
Option 2 : 300

Detailed Solution

Concept approach

450 × 20 = M × 30

⇒ M = 300