A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 2/5 of the work is finished. How many additional men must be employed so that the work is completed on time, each man now working 9 hours a day?

  1. 35
  2. 30
  3. 40
  4. 45
Answer (Detailed Solution Below)
Option 1 : 35

Detailed Solution

Concept approach

105 × 25 × 8/(2/5) = x × 25 × 9/(3/5)

⇒ x = 105 × 8 × 3/(9 × 2) = 140

⇒ additional 35