A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They start the work together and completed the work such that B was not working on last 2 days and A did not work in last 3 days. In how many days (total) was the work completed?

(SSC CGL Mains 2021 (08 Aug 2022))
(SSC CGL 2021 Tier-II (08.08.2022))
  1. 82/7 days
  2. 79/7 days
  3. 65/7 days
  4. 72/7 days
Answer (Detailed Solution Below)
Option 4 : 72/7 days

Detailed Solution

Concept approach

LCM 56: A = 4, B = 2, C = 1; T total days: A works T − 3, B works T − 2

4(T − 3) + 2(T − 2) + T = 56

⇒ 7T = 72

⇒ T = 72/7 days