P, Q, and R can complete a work in 12, 16, and 24 days respectively. They start together, but P leaves after 3 days and Q leaves 2 days before the completion of the work. In how many days is the work completed?

(SSC CGL 2026 (8 Oct, Shift 2))
  1. 41/5 days
  2. 52/5 days
  3. 82/5 days
  4. 91/5 days
Answer (Detailed Solution Below)
Option 3 : 82/5 days

Detailed Solution

Concept approach

Total = 48 units: P = 4, Q = 3, R = 2 per day

Let total days = T: P 3 days, Q (T − 2) days, R T days

12 + 3(T − 2) + 2T = 48

⇒ 5T = 42

⇒ T = 8⅖ days