A and B working together can finish a piece of work in 8 days while B alone can do it in 24 days. In how many days can A alone finish the work?

(SSC CGL Tier-1 2023 (20 Jul · Shift 3 · 2:30 PM))
  1. 10
  2. 16
  3. 12
  4. 14
Answer (Detailed Solution Below)
Option 3 : 12

Detailed Solution

Concept approach

LCM 24

⇒ A+B = 3, B = 1

⇒ A = 2

⇒ 24/2 = 12 days