P and Q together can complete a work in 20 days. R alone can complete the same work in 30 days. P, Q and R together can do the same work in how many days?

(SSC GD Constable 2026 (08 May 2026, Shift 2))
  1. 12
  2. 10
  3. 11
  4. 13.5
Answer (Detailed Solution Below)
Option 1 : 12

Detailed Solution

Concept approach

P + Q = 1/20, R = 1/30

⇒ 3/60 + 2/60 = 5/60 = 1/12 per day

⇒ 12 days