Selection KeySelection KeyFree Mock Test
View this question in:

A is 40% more efficient than B. How much time will they take to work together to complete a job, which A alone could have done in 31 days?

(SSC CGL Tier-1 2023 (21 Jul · Shift 4 · 5:15 PM))
  1. 217/12 days
  2. 515/32 days
  3. 215/12 days
  4. 517/32 days
Answer (Detailed Solution Below)
Option 1 : 217/12 days

Detailed Solution

Concept approach

A : B = 140 : 100 = 7 : 5

⇒ A 31 days

⇒ work = 7 × 31 = 217 units

⇒ together 12 units/day

⇒ 217/12 days